Copy a Sub Project
Sub Projects
You can copy a sub project in the same drawing-model pair of the main project, or to another drawing-model pair of the main project.
- Select the sub projects.
- Right-click to open the context-sensitive menu.
- Select Copy Sub Project.
- Select the drawing-model pair to which you wish to copy the sub project. Do either of the following:
- Select the open drawing-model pair.
- Select another drawing-model pair of the project.
- Select a reference point.
The selected drawing-model pair is activated.
- If necessary, use auxiliary functions before specifying the location.
- Select the location.
- Quit by pressing the Esc key.
Note: The height of the sub project in relation to the absolute origin will change. The sub project will be located in the new drawing-model pair so that its height in relation to the floor base height remains the same as in the original drawing-model pair.