Renumber Sub Projects

Sub Projects

If you defined labels, or numbers, for the sub projects when adding them, you can later renumber the sub projects.

  1. Select the sub projects.
  2. Do either of the following:
    • Select Sub Project | Renumber.
    • Right-click to open the context-sensitive menu, and select Renumber Sub Projects.
  3. Enter the first label (a possible prefix and a sequential number, for example Flat_1) in the dialog box.
  4. Confirm by clicking OK.

The label is displayed in the floor plan and the material report.

Note:
  • If you try to assign an existing label to a sub project, the program will automatically find the next available number.
  • You can move the label from the grip point.