Extract a Building Group to the Main Project

Sub Projects

A building group added to the main project is a single entity whose building components you cannot separately handle. When the main project design has reached a stage at which it becomes necessary to edit the building components of the building group, you can extract the building group to the main project as follows:

  1. Select the building group in the floor plan or the model. Select several building groups by holding down the Ctrl key, or use an area selection.
  2. Right-click to open the context-sensitive menu.
  3. Select Extract Sub Project to This Project.

The program will copy the building components in the building group's drawing-model pairs to the corresponding drawing-model pairs in the main project. The drawing-model pairs correspond to each other when they have the same ordinal number (ORDER).

Note: The connection to the building group project is severed and the changes made to the building group project will no longer be updated in the main project.