Copy Drawings and Databases

  1. On the tab, in the Documents group, click Copy Drawings and Databases.
  2. Select Copying tab.
  3. Select the Source Project and select OK.
  4. Select in the Drawings field Copy from Source Project. Select the drawings from the list.
  5. Select in the Databases field.
  6. Select Copy from Source Project.
  7. Select Remove from Active Project.

------------------------------------------------------------

  1. On the tab, in the Documents group, click Copy Drawings and Databases.
  2. Select Settings tab.
  3. Select Use search form for base project.
  4. Select Log copy operations (copylog.txt).
  5. Select Select from saved drawing revisions.

--------------------------------------------------------------------

Copy options

  1. On the tab, in the Documents group, click Copy Drawings and Databases.
  2. Select Settings tab. Click Copy options.
  3. Select Use automatic numbering to copies.
  4. On the tab, in the Documents group, click Don't update drawing during copy.
  5. On the tab, in the Documents group, click Update reference drawing references.

Note

  • Revision settings do not apply when project revision system has not been upgraded.