Save Changes to a Smart Model
Sub Projects
You can edit the smart model as usual by opening the model for editing and saving the changes. When you open the main project, the program suggests updating the smart models in the main project.
If you are editing a smart model in the main project, save the changes as follows:
- Select the smart model.
- Select in the object tree
- Set the object tree visible by selecting the Model tab in the left side browser.
- Open the branch Smart models.
- Select the ID of the smart model.
- Select in the drawing or model window of the main project
- Select one object that belongs to the smart model.
- Click the + grip point to select the entire model.You can also select this function from the tool strip.
- Select in the object tree
- Do either of the following:
- Select Smart Model | Save | Save.
- Right-click to open the context-sensitive menu, and select Smart Model > Save [ID of smart model].
- Update the changes to other smart models with the same ID in the same main project.
In other main projects, the up-to-dateness of the smart model is checked when the project is opened, in which case you can choose to update the model.